2018 has been an year of erratic weather conditions. Firstly, the much anticipated snow never came after initial onslaughts. Then rains followed no pattern and HP was adversely hit with many roads getting washed away and slopes tumbling down due to flash floods and cloud bursts. Barring peak summer months, work could not progress too well due to unforeseen interruptions every fortnight or so. Slowly and steadily, we kept at it and despite whatever nature threw at us, we remained pro-active most of the times. Some pictorial references.....
As the work on the first block was going on and its third level was raised, we could squeeze in enough time to start the work on the second block. We froze the plan to have three floors (each with two rooms) in the first block and two floors (each with two rooms) in the second block. The third structure, kitchen and cafe, would have one single storey with another floor only on one side. The whole layout was visualised as three steps kind of an elevation with one storey of the third block, two storeys of second block and three storeys of the first block- all echeloned in a sequential progression.
An idea to use local mud plaster (earth+pine needles+ cow dung) on the outside was tried and it looked pretty good. Such a plaster, in addition to adding rustic touch to the settings, shall also act as a good insulator of temperature.
Chamba Slates (with distinct bluish grey hue) arrived and were stacked up as we went around hunting for a suitable generator set since the available power supply didn't have sufficient voltage required to run the welding set smoothly.
With slab on the ground floor of the second block laid and compulsory wait of three weeks enforced, we started bringing up the third block that would have a covered verandah, a dining area and a kitchen. Staff quarters shall come up on top of kitchen area. The facade of this block towards approach path has been constructed using local stones.
The third block is now set to take on roof work. Far left is kitchen on the ground floor and staff room on top; middle is an internally raised roof to accommodate 1.5 levels of seating and to the right is the covered verandah (single storey height).
Concurrently, work on the roof of the first block was happening (we were proactive, after all!) This is how the roof looks like from inside. Each slate gets anchored to the steel frame (or wood as the case may be) through a nail that is welded to the frame and driven through a hole in the slate. Each slate has an overlap of 4 inches and nail gets hidden under the overlap. It is a thing of beauty but is demanding and a labour intensive job.
This frame gives out the whole picture. The first wall (facade) towards approach path/future parking is made of stone and a few bricks (as replacement for wood in a typical Kath-kuni construction methodology). It shields staff quarter on top and kitchen below. Joined to this structure (as part of third block itself) are dining area on 1.5 levels and an open verandah. After the gap, is the second block with slab on the ground floor (scaffolding /shuttering seen). Another gap and we have three floors of the first block!
With roof work on first and third blocks now complete, things have started to look more orderly. While the blocks are coming up well, what can't be overlooked or ignored is the natural beauty of the place. It is green on all sides and once clouds clear off, we get an amazing view of the mountains across Barot/Uhl valley below.
Small niches here and there are being used for future storage and so on.
We are already into October (3rd week) of 2018. As I key in these words, first floor walls of the second block are being raised. Once that has been done, roof shall be set on top. However, concurrently, work on interiors has commenced. Six washrooms are ready sans fittings and panelling work in six rooms is on. More about that in the next post!








































